Project Portfolio · Multi-Family

Roof, Siding and Gutter Replacement Across a 31 Building Condo Community

Once insurance approved a condo roof and siding replacement, plus new gutters, for a 31 building community in Oswego, we were brought in to install it. We replaced all three on every building, one building at a time, so the roughly 235 households living there always knew what was coming and when.

31
condo buildings re-roofed and re-sided
~2,300
squares of architectural shingles
3
months for roofs, siding and gutters
Finished Exterior

The Finished Exterior

Project Overview

The Job

Insurance had already approved a full exterior on all 31 buildings when the restoration company managing the claim brought us in to handle the install: tearing off, putting it back right, and keeping it moving on a property where people live and park every day.

We worked alongside the restoration company, the management company running the community, and the board, and kept all three up to date on which buildings were next. On every building:

  • Full tear-off and a new roof
  • Architectural asphalt shingles
  • New CertainTeed vinyl siding in Flagstone
  • New gutters
  • Skylight replacement
Project Details
Location
Oswego, IL
Property
Condo community, about 235 units
Buildings
31 condo buildings
Roof area
About 230,000 sq ft (roughly 2,300 squares)
Project type
Insurance claim restoration
Roofing
Architectural asphalt shingles
Siding
CertainTeed vinyl siding in Flagstone
Timeline
Roofing about 4 weeks, full exterior about 3 months
Completed
2025
Roof replacement underway on several condo buildings at once in an Oswego, IL community
Tear-off underway on a few buildings at a time
New gray architectural shingles next to the original brown roof on a condo building in Oswego, IL during a building by building re-roof
New gray shingles going on next to the original brown roof
Architectural shingle roof on a condo building in Oswego, IL
A finished roof, with new siding up next
Project Timeline

How We Ran the Condo Roof and Siding Replacement

Set the order

We planned the building sequence with the board, management company and restoration company before the first tear-off.

Give residents notice

Every unit got a notice on its door 48 hours before work started on that building.

Roofs first

We tore off and replaced roofs building by building, with up to four going at once. Crews worked one section of roof at a time and only tore off what they could finish that day. If a building took more than one day, the sections we hadn’t reached yet kept their old roof until we got to them, so nothing was left open overnight and no tarps were needed. During tear-off, we leaned boards over garage doors and windows to keep debris off them.

Siding follows the roof

No building got siding until its roof was done. Up to four other buildings were being resided at the same time, so roofing and siding crews were never stacked on the same building.

Gutters last

New gutters went on after the siding, so they hang on finished walls.

Why that order? Tearing off a roof sends debris down the walls, and the flashing where the roof meets the wall has to be in place before siding goes over it. Doing it the other way risks damaging brand new siding.

Installer putting up new gray blue vinyl siding over house wrap on a two story condo building in Oswego, IL, with the old cream siding still on the next unit
New siding going on after the roof was done
Condo building in Oswego, IL wrapped in house wrap with ladders set up for siding replacement, new roof already finished
A building wrapped and ready for siding, with its new roof already on

Planning roofs and siding across your whole community?

Restoration companies bring us in to install approved claims, and associations bring us in to run the whole exterior: roofs, siding and gutters. Tell us how many buildings you have and we’ll walk the property.

Residents

Keeping Residents in the Loop

About 235 households lived here through the whole job, so communication was half the work.

  • Nobody went to bed under an open roof. Crews only tore off what they could close up the same day.
  • Every unit got a notice on its door 48 hours before work started on that building.
  • Our team talked with homeowners every day, answering questions and letting them know when their building was up.
Schedule

Four Weeks of Roofing, Three Months in All

Roofing on all 31 buildings took about four weeks, weather days included. Siding takes longer with all the finer detail work, so the full exterior, gutters included, took about three months. With up to four buildings being re-roofed while four others were being re-sided, the job never stalled waiting on one crew.

Outcome

The Result

The full condo roof and siding replacement, all 31 buildings with new roofs, CertainTeed siding and gutters, wrapped up in about three months in 2025.

The board had one installer for the whole exterior, start to finish, and both the management company and the restoration company have brought us back for more work since.

Finished condo roof and siding replacement on a building in Oswego, IL, with new gray shingles, gray blue siding and white trim
Next Step

Got a community exterior project coming up?

Whether it’s an approved insurance claim or a planned replacement, we’ll walk the property and give your board a clear plan for roofs, siding and gutters. Restoration companies bring us in for installs like this one, and we’re just as glad to run a condo and HOA roof replacement start to finish for an association.