Apartment Complex Roof Replacement Across 36 Buildings in Louisville, KY
When the owner of a 36 building apartment community in Louisville, KY planned an apartment complex roof replacement, they brought us in to install it. We put on about 4,000 squares of architectural shingles in 9.5 weeks, with residents living in every building the whole time.
The Finished Roofs
The Job
This was a planned replacement, part of the property’s capital maintenance. No storm, no insurance claim. For this particular project, the owner preferred to choose the shingle and supply the materials, and we handled the install.
That install covered 34 apartment buildings and 2 auxiliary buildings, about 4,000 squares in all:
- Full tear-off on every roof
- Sheathing replaced wherever the deck needed it
- Drip edge, ice and water, and underlayment
- New flashing and pipe boots
- Architectural asphalt shingles
- Ridge vent
- Location
- Louisville, KY
- Property
- Apartment community
- Buildings
- 34 apartment buildings, 2 auxiliary buildings
- Roof area
- About 4,000 squares (roughly 400,000 sq ft)
- Project type
- Capital maintenance re-roof
- Roofing
- Architectural asphalt shingles
- Timeline
- 9.5 weeks, June to August 2026
- Completed
- 2026
How We Ran the Apartment Complex Roof Replacement
Build the schedule
Before the first tear-off, we worked out the building order with the community management team. They handled communication with residents, and we gave them a schedule they could share so everyone knew when crews would be at their building.
Set up each building
Crews covered landscaping with tarps and fenced off the areas where old material was coming down. A boom lift set the new shingles right on the roof, so bundles weren’t being carried through walkways and parking lots.
One section at a time
Crews only tore off what they could finish that same day. Sections we hadn’t reached yet kept their old roof, so nothing was left open overnight. Once a section was down to the deck, we checked the sheathing and replaced any that needed it before anything new went on.
Installation
Drip edge, ice and water and underlayment went down first, then new flashing and pipe boots, then the shingles. Ridge vent finished off each roof.
Keep it moving
We had 4 to 5 buildings going at once and averaged about 400 squares a week. Crews cleaned up around each building before moving on to the next one.
Planning a re-roof across your whole community?
Owners and property managers bring us in to install, or to run the whole job from picking the shingle to the final cleanup. Tell us how many buildings you have and we’ll walk the property.
Working Around Residents
Every building stayed occupied for the whole job.
- Nobody went to bed under an open roof. Crews only opened what they could close the same day.
- The community management team kept residents in the loop with the schedule we built together.
- A boom lift set shingles right on the roof, and crews kept walkways safe and clear.
About Those 9.5 Weeks
Louisville summers get hot, and it’s a lot hotter up on a roof than it is down on the ground. Our 9.5 weeks counts every working day, Monday through Friday, from start to finish. That includes rain days and the days that were simply too hot to be up there. We’d rather lose a day than push a crew through dangerous heat.
The Result
The full apartment complex roof replacement, all 36 buildings and about 4,000 squares, wrapped up in 9.5 weeks between June and August 2026.
Residents stayed home the entire time, and the owner has told us we’re on their shortlist when their next roofing project comes up.
Got a community re-roof coming up?
Some owners like to choose and supply their own materials, like on this job, and we’re glad to work that way. We’re just as glad to handle that part for you: helping you pick the right shingle, ordering everything, and getting it delivered to the right place at the right time. That way your whole multi-family roof replacement runs through one team.
(888) 643-9247